Follow Along On Embarq's Home Show Expo Progress!

Follow along as our 2026 Home Show home comes to life. From initial planning to final finishes, this page is your inside look at the craftsmanship, design decisions, and progress happening every step of the way.

Because at Embarq, details don’t follow the design—they define it.

2026 Embarq Home Show Expo Updates

Untitled design (7)

What’s Happening Now

We’re making exciting progress this month. This month marks a major step forward as the home continues to take shape. With key phases underway, you’ll start to see spaces defined, features installed, and the vision becoming reality.


Insights from Lera, Embarq's Project Manager

Explore the design details and decisions of the 2026 Home Show Expo Home with our incredible project manager, Lera!

How It All Started

Every great home begins with a vision. Below, you’ll find a timeline of the key milestones that have brought this Home Show house from concept to construction. From excavation to foundation and framing, this is where the journey begins.

July 2026

Patio stonework was installed, custom built-ins were built, marble detailing was installed, a putting green was installed, and custom kitchen features, like the vent hood and ceiling detail, were installed.

 

 

 

 

 

 

 

 

 

 

May 2026

Drywall was completed, exterior painting began, back patio fireplace was installed, exterior stone work began, interior trim work was started, cabinets were delivered, and tile installation began!

 

 

 

 

March 2026

Framing details began, metal roof + shingles were installed, rough ins for utilities were completed, and pool is ready for install. 

 

 

 

January 2026

Excavation began, over dig and rock completed, and the foundation was laid.

|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|

 

 

June 2026

Concrete and patio work were completed, the pool shed was built, windows were installed, siding was completed, and custom tile was installed throughout the house!

 

 

 

 

 

 

 

 

April 2026

Drywall + Insulation began inside, Bulkheads to conceal utilities in the ceiling were completed, Siding was delivered + in ready for install!

 

 

 

February 2026

Framing began + drop trusses were installed. 

 

Meet the Expert Minds at Embarq Signature Homes

Building a custom home is a team effort, and this video from Embarq Signature Homes highlights the various professionals involved. From operations and project management to construction and sales, each member brings their expertise and passion to the table. Watch to learn more about the team's commitment to quality, craftsmanship, and customer satisfaction.

What You Don't See is What Matters Most

What you see is beautiful. What you don't see is what makes the difference. From the foundation to the framing and every detail in between, we believe a great home starts with quality craftsmanship behind the walls. Join Seamus as he walks us through the quality behind the 2026 Embarq HomeShow Home.